Downtown Streetscape Update 9.22.23

This week the contractor finished installing brick pavers at the intersection of W Main and Spring St, they hope to install polymetric sand to finalize the bricks on Saturday (9/23) and reopen the intersection afterwards. Landscaping and the resurfacing of W Main St were also completed this week. Brick crosswalks will be installed beginning next week at W Main and High Rd. Two-way traffic will be maintained during this process that will take approximately two weeks.



5 views0 comments

Recent Posts

See All

Downtown Streetscape Update 9.29.2023

The new detour plan remained in place this week as the contractor continues working to install the brick paver crosswalks at the intersection of High Rd and W Main St. This detour is expected to remai