Downtown Streetscape Update 9.22.23
This week the contractor finished installing brick pavers at the intersection of W Main and Spring St, they hope to install polymetric sand to finalize the bricks on Saturday (9/23) and reopen the intersection afterwards. Landscaping and the resurfacing of W Main St were also completed this week. Brick crosswalks will be installed beginning next week at W Main and High Rd. Two-way traffic will be maintained during this process that will take approximately two weeks.