Work continued this week on underground utilities on the South side of W Main St. The electrical subcontractor is nearly finished with installations and concrete foundations are scheduled to be completed early next week. Irrigation conduits have also been installed. Concrete sidewalks will be installed next followed by brick pavers. The contractor is currently anticipating beginning the installation of the medallion at the intersection of W Main and Spring St on Monday, August 21st. Traffic patterns will be adjusted accordingly at that time.