This week, brick pavers were installed on the North side of W Main St. in addition to concrete work. Sawcutting and concrete curb & sidewalk removals began on the South side of W Main St. late this week.


With this, the focus of construction has now shifted to the South side of W Main St. During this phase no on-street parking will be available in an effort to preserve the most efficient flow of traffic. Following the completion of concrete removals, underground utility work will begin.







5 views0 comments

Recent Posts

See All

The new detour plan remained in place this week as the contractor continues working to install the brick paver crosswalks at the intersection of High Rd and W Main St. This detour is expected to remai