top of page
Main at Spring_edited.jpg
Search
  • tbassuener

Downtown Streetscape Update 6/2/23

The electrical contractor has finished work on the North side of W Main St. Irrigation lines and brick pavers are the next items to be installed on the North side. With this, the contractor is anticipating shifting work to the South side of W Main St. on June 19th.



8 views0 comments

Recent Posts

See All

Downtown Streetscape Update 9.29.2023

The new detour plan remained in place this week as the contractor continues working to install the brick paver crosswalks at the intersection of High Rd and W Main St. This detour is expected to remai