Concrete sidewalk was poured along the north side of W Main St. this week. Additionally, concrete foundations were poured for utility structures and a water main tap was performed to connect the irrigation lines to the Village’s water supply system. The contractor expects to finish pouring concrete next week in addition to installing brick pavers and landscaping.