top of page
Main at Spring_edited.jpg
Search
  • tbassuener

Downtown Streetscape Update 5/5/2023

Underground utility work continued this week as the contractor worked to ensure safe the installation of electrical conduit for new lighting and traffic signals. This installation is expected to be completed mid-next week. Following this, the installation of irrigation lines will occur. All construction is still occurring on the North side of W Main St.




5 views0 comments

Recent Posts

See All

Downtown Streetscape Update 9.29.2023

The new detour plan remained in place this week as the contractor continues working to install the brick paver crosswalks at the intersection of High Rd and W Main St. This detour is expected to remai

Comments


bottom of page