top of page
Main at Spring_edited.jpg
Search
  • tbassuener

Downtown Streetscape Update 5/19/2023

Underground utility work continued on the North side of W Main Street this week. Availability of supplies for the project has caused minor delays, but the project still remains within a week of planned schedule. The contractor expects to complete the North side of the project within the next two weeks. Following this, the next phase of construction will be to complete similar tasks on the South side of W Main Street.



13 views0 comments

Recent Posts

See All

The new detour plan remained in place this week as the contractor continues working to install the brick paver crosswalks at the intersection of High Rd and W Main St. This detour is expected to remai

bottom of page