Underground utility work continued on the North side of W Main Street this week. Availability of supplies for the project has caused minor delays, but the project still remains within a week of planned schedule. The contractor expects to complete the North side of the project within the next two weeks. Following this, the next phase of construction will be to complete similar tasks on the South side of W Main Street.