Week 2 of the Village’s Downtown Streetscape Project is in the books! This week temporary traffic signals were installed and preliminary project setup was completed.
Next week, the contractor anticipates performing fire hydrant relocations, sawcutting, and curb & sidewalk removals along the north side of W. Main St.